Q-2, r. 7.1 - Regulation respecting sand pits and quarries

Full text
4. (Revoked).
O.C. 236-2019, s. 4; O.C. 871-2020, s. 2.
4. The following changes are subject to a prior amendment authorization under the first paragraph of section 30 of the Act:
(1)  enlarging a quarry or sand pit beyond an area or limits prescribed in the authorization;
(2)  changing the redevelopment and restoration plan of a quarry or sand pit.
O.C. 236-2019, s. 4.
In force: 2019-04-18
4. The following changes are subject to a prior amendment authorization under the first paragraph of section 30 of the Act:
(1)  enlarging a quarry or sand pit beyond an area or limits prescribed in the authorization;
(2)  changing the redevelopment and restoration plan of a quarry or sand pit.
O.C. 236-2019, s. 4.